02 07
[Ken Fujimoto's solar report] Finally realized! Solar power plant is set up at the foot of Mt. Fuji (Part 1) --Delivery WATCH

 The dream of "making a large solar power plant", which has been a plan for two years and eight months, has finally been realized on May 19th.At the foot of Mt.

 However, 52kW is a system that produces about 15 power of general households.It's not a large -scale, and in fact, my own share is half a contract.

【藤本健のソーラーリポート】ついに実現! 太陽光発電所を富士山麓に設置(前編) - 家電 Watch

 Nevertheless, the joy of starting to start is full.In my solar power plant installation plan, it is the first step, but I would like to introduce what this is and the road to this point.

ついに太陽光発電所を稼働富士河口湖町に設置

 As you may have seen, I wrote an article last August, "I started a 50 kW solar power generation business in Kyushu" three times.The title was "I started", but as I wrote there, it actually made a contract of 20 million yen with a full debt, and the location of the power plant, rather than installing a power plant.It was an ambiguous situation that it was not clear.

 However, in September immediately after the article, a so -called "Kyuden Shock" case occurred.From there, the situation in Japan's solar power generation turned dark.Kyuden Shock is a declaration that Kyushu Electric Power has declared a new connection contract holding of solar power system connections, such as "the supply and demand balance of electricity will be lost."

 That was a big incident that spread to Hokkaido Electric Power, Tohoku Electric Power, Shikoku Electric Power, and Okinawa Electric Power.I think there are many ways to interpret it, but even if you look at the subsequent solar power generation bashing reports, the movement of the nuclear power plant restart, and the 2030 energy mix shown by the government, the renewable energy, especially solar power generation, are tremendous headwinds.There is no doubt that you are in.